The Yarra Valley Trail continues its progress with construction underway along multiple sections of the trail.
Yarra Valley Trail Stage 1B – Yering to Yarra Glen
In addition to 1.2km of new trail between Yering and Melba bend, this stage of the project includes two heritage railway bridges. The structures are being upgraded with the timber trestle base being retained. Onsite work will resume in mid-January, and be completed by April 2025.
The tender process is underway for the next section of trail to the Yarra River, with construction to commence in mid 2025.
Yarra Glen Northern Loop
Walkers, cyclists and horse riders are already enjoying the completed sections of the Yarra Glen Northern Loop, offering spectacular views over the Valley.
Construction of 1.2km of new trail on Gulf Road is complete. Additional construction on Gulf Road to Melba Highway, including bridge delivery, is planned for late January 2025.
Yarra Valley Trail Stage 2A – Yarra Glen to Tarrawarra
Initial work to upgrade the Yarra Glen River Walk is complete.
The remaining 3.8km of the shared use trail will be located within the Healesville railway corridor, on the southern side of the railway line which is being restored by Yarra Valley Railway.
A Cultural Heritage Management Plan is in development, and an initial Flora and Fauna Assessment, Arboricultural Assessment and Feature Survey have been undertaken.
The design process for the bridges and boardwalks is underway and a Planning Permit application will be lodged in early 2025.