Stage 1a of the Yarra Valley Trail is nearing completion with the trail set to open by Christmas.

Bridge construction is currently underway, pile driving and abutments have been installed. The piles are being driven down to bedrock, 12 metres below the surface. Bridge installations will be completed next week.

The Trail surfacing is also currently underway with roughly 1km being laid per day.

Works to install signage and fencing will continue over the coming weeks.